Chapter 7: Welding Procedures – WPS, PQR, and WPQ

 

Chapter 7: Welding Procedures – WPS, PQR, and WPQ


📘 7.1   is a Welding Procedure Specification (WPS)?

A Welding Procedure Specification (WPS) is a detailed, written document that provides direction to the welder for making a weld according to code requirements.

✅ It ensures repeatability, quality, and compliance.


🧪 7.2 Procedure Qualification Record (PQR)

A PQR is a record of test results used to verify that a welding procedure (WPS) will produce an acceptable weld.

📌 It contains:

Mechanical test results (tensile, bend, impact)

Visual & NDT reports
Actual welding parameters used during testing

Relationship:
👉 PQR validates the WPS.


👨‍🏭 7.3 Welder Performance Qualification (WPQ or Welder Qualification Test – WQT)

WPQ proves that a specific welder can deposit sound weld metal using a particular process.

🔎 It's based on:

A visual inspection

NDT (e.g., RT/UT)
Mechanical tests (if required)

🧾 Result: Certificate issued showing the range of qualification (position, diameter, thickness).


🧰 7.4 WPS Contains the Following Parameters:

ParameterExamples
Welding ProcessSMAW, GTAW, FCAW, SAW
Base MaterialASTM A36, IS2062
Filler MaterialE7018, ER70S-6
Position1G, 3G, 5G, etc.
Preheat & Interpass Temp100°C, 150°C
Amperage / Voltage90–120 A / 20–30 V
Travel Speedmm/min
Shielding GasArgon, CO₂

🔎 7.5 Importance of WPS/PQR/WPQ in QA/QC

  1. WPS ensures that welding is performed in a controlled and qualified manner

  2. PQR proves that the procedure can make a sound weld

  3. WPQ certifies that the welder is skilled

🚨 If any of these are missing, the entire fabrication job may be rejected by the client or third-party inspector (TPI).


🏭 7.6 Practical Example: Pressure Vessel Fabrication

Project: ASME Section VIII Pressure Vessel

WPS developed and tested by fabricator

PQR performed with bend & tensile test
Welders qualified for 6G SMAW on CS plate
All welds inspected with RT
Final reports submitted for third-party approval

📌 Without WPS/PQR, the job would not be accepted, even if the weld looks fine.


🔎 7.7 Codes Referenced in WPS/PQR/WPQ

CodeDescription
ASME Section IXQualification of Welders & Procedures
API 1104Pipeline welding
AWS D1.1Structural steel welding
ISO 15614Welding procedure qualification

📂 7.8 Traceability

Every weld joint should be traceable to:

Welder ID (from WPQ)

WPS No.
PQR No.
Welding date
Weld map

🧾 All these must be included in QA/QC documentation submitted at the end of the project.


Common QA/QC Issues in Welding Documentation:

Using unqualified welders

Missing or incorrect WPS
PQR doesn’t match actual job parameters
No documentation for repair welds
Mismatch in filler metal and base material

📌 7.9 Summary

WPS defines how welding should be done

PQR validates that the procedure works
WPQ ensures welder skill is proven
All are mandatory in most mechanical and piping projects

Quiz: Welding Documentation (WPS/PQR/WPQ)


Q1. What does WPS stand for?
A) Weld Process Schedule
B) Welding Performance Sheet
C) Welding Procedure Specification
D) Welded Pipe Standard
🟩 Correct Answer: C


Q2. Which document is used to validate that a welding procedure can produce sound welds?
A) WPQ
B) WPS
C) PQR
D) ISO 9001
🟩 Correct Answer: C


Q3. WPQ certifies the:
A) Quality of welding rod
B) Qualification of the welding inspector
C) Qualification of the welder
D) Type of base material used
🟩 Correct Answer: C


Q4. Which ASME section deals with Welding Qualifications?
A) Section V
B) Section VIII
C) Section IX
D) Section II
🟩 Correct Answer: C


Q5. If a welder is qualified in 6G position, they can weld in:
A) Only flat position
B) Only vertical position
C) All positions
D) Overhead only
🟩 Correct Answer: C


Q6. Which of the following is NOT included in a typical WPS?
A) Welding process
B) Voltage & current range
C) Welder’s name
D) Preheat temperature
🟩 Correct Answer: C


Q7. The PQR must include:
A) Welding process and base material only
B) Welder’s opinion
C) Mechanical test results (like tensile & bend tests)
D) Client name only
🟩 Correct Answer: C


Q8. Why is traceability important in welding QA/QC?
A) To track welder's salary
B) For future promotions
C) To ensure each weld is linked to a qualified person and document
D) For quality of paint
🟩 Correct Answer: C


Q9. Which code governs structural welding practices?
A) API 1104
B) AWS D1.1
C) ISO 9712
D) ASME B16.5
🟩 Correct Answer: B


Q10. A project’s welds were rejected because no PQR was submitted. This violates:
A) Safety law
B) Financial law
C) Code compliance
D) All of the above
🟩 Correct Answer: C


homeacademy

Home academy is JK's First e-learning platform started by Er. Afzal Malik For Competitive examination and Academics K12. We have true desire to serve to society by way of making educational content easy . We are expertise in STEM We conduct workshops in schools Deals with Science Engineering Projects . We also Write Thesis for your Research Work in Physics Chemistry Biology Mechanical engineering Robotics Nanotechnology Material Science Industrial Engineering Spectroscopy Automotive technology ,We write Content For Coaching Centers also infohomeacademy786@gmail.com

إرسال تعليق (0)
أحدث أقدم