Chapter 7: Welding Procedures – WPS, PQR, and WPQ
📘 7.1 is a Welding Procedure Specification (WPS)?
A Welding Procedure Specification (WPS) is a detailed, written document that provides direction to the welder for making a weld according to code requirements.
✅ It ensures repeatability, quality, and compliance.
🧪 7.2 Procedure Qualification Record (PQR)
A PQR is a record of test results used to verify that a welding procedure (WPS) will produce an acceptable weld.
📌 It contains:
Mechanical test results (tensile, bend, impact)
Visual & NDT reportsActual welding parameters used during testing
Relationship:
👉 PQR validates the WPS.
👨🏭 7.3 Welder Performance Qualification (WPQ or Welder Qualification Test – WQT)
WPQ proves that a specific welder can deposit sound weld metal using a particular process.
🔎 It's based on:
A visual inspection
NDT (e.g., RT/UT)Mechanical tests (if required)
🧾 Result: Certificate issued showing the range of qualification (position, diameter, thickness).
🧰 7.4 WPS Contains the Following Parameters:
Parameter | Examples |
---|---|
Welding Process | SMAW, GTAW, FCAW, SAW |
Base Material | ASTM A36, IS2062 |
Filler Material | E7018, ER70S-6 |
Position | 1G, 3G, 5G, etc. |
Preheat & Interpass Temp | 100°C, 150°C |
Amperage / Voltage | 90–120 A / 20–30 V |
Travel Speed | mm/min |
Shielding Gas | Argon, CO₂ |
🔎 7.5 Importance of WPS/PQR/WPQ in QA/QC
-
WPS ensures that welding is performed in a controlled and qualified manner
-
PQR proves that the procedure can make a sound weld
-
WPQ certifies that the welder is skilled
🚨 If any of these are missing, the entire fabrication job may be rejected by the client or third-party inspector (TPI).
🏭 7.6 Practical Example: Pressure Vessel Fabrication
Project: ASME Section VIII Pressure Vessel
WPS developed and tested by fabricator
PQR performed with bend & tensile testWelders qualified for 6G SMAW on CS plate
All welds inspected with RT
Final reports submitted for third-party approval
📌 Without WPS/PQR, the job would not be accepted, even if the weld looks fine.
🔎 7.7 Codes Referenced in WPS/PQR/WPQ
Code | Description |
---|---|
ASME Section IX | Qualification of Welders & Procedures |
API 1104 | Pipeline welding |
AWS D1.1 | Structural steel welding |
ISO 15614 | Welding procedure qualification |
📂 7.8 Traceability
Every weld joint should be traceable to:
Welder ID (from WPQ)
WPS No.PQR No.
Welding date
Weld map
🧾 All these must be included in QA/QC documentation submitted at the end of the project.
❌ Common QA/QC Issues in Welding Documentation:
Using unqualified welders
Missing or incorrect WPSPQR doesn’t match actual job parameters
No documentation for repair welds
Mismatch in filler metal and base material
📌 7.9 Summary
WPS defines how welding should be done
PQR validates that the procedure worksWPQ ensures welder skill is proven
All are mandatory in most mechanical and piping projects
Quiz: Welding Documentation (WPS/PQR/WPQ)
Q1. What does WPS stand for?
A) Weld Process Schedule
B) Welding Performance Sheet
C) Welding Procedure Specification
D) Welded Pipe Standard
🟩 Correct Answer: C
Q2. Which document is used to validate that a welding procedure can produce sound welds?
A) WPQ
B) WPS
C) PQR
D) ISO 9001
🟩 Correct Answer: C
Q3. WPQ certifies the:
A) Quality of welding rod
B) Qualification of the welding inspector
C) Qualification of the welder
D) Type of base material used
🟩 Correct Answer: C
Q4. Which ASME section deals with Welding Qualifications?
A) Section V
B) Section VIII
C) Section IX
D) Section II
🟩 Correct Answer: C
Q5. If a welder is qualified in 6G position, they can weld in:
A) Only flat position
B) Only vertical position
C) All positions
D) Overhead only
🟩 Correct Answer: C
Q6. Which of the following is NOT included in a typical WPS?
A) Welding process
B) Voltage & current range
C) Welder’s name
D) Preheat temperature
🟩 Correct Answer: C
Q7. The PQR must include:
A) Welding process and base material only
B) Welder’s opinion
C) Mechanical test results (like tensile & bend tests)
D) Client name only
🟩 Correct Answer: C
Q8. Why is traceability important in welding QA/QC?
A) To track welder's salary
B) For future promotions
C) To ensure each weld is linked to a qualified person and document
D) For quality of paint
🟩 Correct Answer: C
Q9. Which code governs structural welding practices?
A) API 1104
B) AWS D1.1
C) ISO 9712
D) ASME B16.5
🟩 Correct Answer: B
Q10. A project’s welds were rejected because no PQR was submitted. This violates:
A) Safety law
B) Financial law
C) Code compliance
D) All of the above
🟩 Correct Answer: C