Chapter 17: QA/QC in Project Management & Handover

 

Chapter 17: QA/QC in Project Management & Handover

This chapter focuses on how QA/QC integrates with project management, especially during planning, execution, monitoring, and final project handover stages in the mechanical engineering and construction industries.


📌 1. QA/QC in Project Life Cycle

StageQA/QC Involvement
Project PlanningDefine quality objectives, prepare ITP & QAP
ProcurementVendor inspection, material test certificate review
Fabrication/ExecutionIn-process inspections, NDT, welding inspections
Testing & CommissioningHydrostatic, pneumatic, and functional testing
HandoverDossier submission, punch list clearance, client approval

🧾 2. QA/QC Documentation During Handover

At the end of a project, QA/QC engineers prepare and compile a Final QA Dossier or Quality Handover File, which includes:

Approved Drawings and As-Built Drawings

Material Test Certificates (MTCs)
Welding records (WPS, PQR, WPQ)
NDT Reports (UT, RT, PT, MPI, etc.)
Inspection Reports (Dimensional, Visual)
Hydro/Pneumatic test reports
Calibration certificates
Non-conformance reports & corrective actions
Manufacturer and third-party certificates
Equipment manuals and warranty documents

Client will not accept project completion without this QA file.


⚠️ 3. Punch List & Snagging

  • Punch List: A list of minor outstanding works or defects at project closing.

  • QA/QC Role: Track, document, and ensure timely closure of punch points with corrective action.


4. Quality Audit & Final Inspection

  • Third-party or client audits are conducted.

  • QA/QC team must ensure:

    • Documents are traceable and sequential.

    • Inspection Logs match field execution.

    • No major NCRs are pending.


🏗️ 5. Field Example:

At a refinery shutdown project, delay in submitting QA documentation (hydro test reports, welder logs, MTCs) delayed client approval by 3 weeks, affecting commissioning timeline and penalty clauses. Proper QA/QC coordination from the start would have prevented this.


🧠 6. Project QA/QC Checklists (Mechanical Focus)

ActivityChecklist Required
Pipe WeldingWPS, Welder ID, Fit-up, NDT reports
HydrotestTest pressure, hold time, result
Equipment InstallationAlignment check, grouting report
Pressure Vessel DeliveryMTC, RT, PWHT, dimensional check

🔧 Best Practices for QA/QC at Handover

Start building dossier from Day 1.

Follow ITP and QAP strictly.
Regular internal audits before client audits.
Maintain revision control on documents.
Train team on document filing and tracking.

Chapter 17: MCQs – Project QA/QC & Handover


Q1. What is a "Punch List" in QA/QC?
A) A list of workers on-site
B) A checklist of material suppliers
C) A list of pending works or defects to be completed before handover
D) A document to approve procurement
🟩 Correct Answer: C


Q2. Which of the following documents is not usually included in a QA Dossier?
A) Material Test Certificates
B) Approved Drawings
C) Welding Procedure Specification
D) Bank guarantee letter
🟩 Correct Answer: D


Q3. What is the final outcome of the QA/QC process in a project?
A) Client handover file with complete documentation
B) Lab test of paints
C) Electrical wiring
D) Final cost analysis
🟩 Correct Answer: A


Q4. What is the risk if QA/QC documentation is not submitted on time?
A) Site becomes safer
B) Workload decreases
C) Project delays and client non-approval
D) Faster shutdown
🟩 Correct Answer: C


Q5. Which of these documents verifies the material's origin and quality?
A) NCR Report
B) Material Test Certificate (MTC)
C) ITP
D) Alignment report
🟩 Correct Answer: B


Q6. The primary responsibility for QA/QC handover documentation lies with:
A) Safety Officer
B) Accountant
C) QA/QC Engineer
D) Procurement Engineer
🟩 Correct Answer: C


Q7. Which of the following is a QA activity in project management?
A) Performing hydrotest
B) Issuing purchase orders
C) Preparing Quality Assurance Plan (QAP)
D) Transporting equipment
🟩 Correct Answer: C


Q8. What happens if a pressure vessel is delivered without RT and PWHT records?
A) It will be accepted quickly
B) No impact
C) It may be rejected or returned
D) It will be approved on-site
🟩 Correct Answer: C


Q9. What is an NCR?
A) National Code Requirement
B) Non-Conformance Report
C) New Contractor Record
D) Normal Calibration Report
🟩 Correct Answer: B


Q10. When should QA/QC documentation begin on a project?
A) After construction ends
B) Just before audit
C) From project start
D) After handover
🟩 Correct Answer: C


homeacademy

Home academy is JK's First e-learning platform started by Er. Afzal Malik For Competitive examination and Academics K12. We have true desire to serve to society by way of making educational content easy . We are expertise in STEM We conduct workshops in schools Deals with Science Engineering Projects . We also Write Thesis for your Research Work in Physics Chemistry Biology Mechanical engineering Robotics Nanotechnology Material Science Industrial Engineering Spectroscopy Automotive technology ,We write Content For Coaching Centers also infohomeacademy786@gmail.com