Chapter 18: QA/QC Interview Preparation & Field Challenges

 

Chapter 18: QA/QC Interview Preparation & Field Challenges

This final chapter prepares you for real-world interviews and on-site situations faced by QA/QC engineers in mechanical industries (oil & gas, power plants, fabrication yards, refineries, HVAC projects, etc.).


🎯 1. Common QA/QC Interview Questions

QuestionPurpose
Explain the difference between QA and QCChecks concept clarity
What is WPS, PQR, and WPQ?Welding knowledge
How do you handle an NCR?Problem-solving skill
What are the steps in hydrostatic testing?Field knowledge
How do you prepare a final QA/QC dossier?Project experience

🛠️ 2. Practical Field Challenges (with Solutions)

ChallengeSolution
Client rejected material due to missing MTCAlways verify MTCs and vendor compliance at receipt
Welder used wrong electrodeCross-check WPS, give toolbox talk, and issue NCR
Inspection agency delayed reportsMaintain parallel documentation; push through follow-up
Paint thickness not as per specRe-inspect and re-coat; document with DFT (Dry Film Thickness) gauge
Site crew skips hold point inspectionTrain team on ITP flow; log incident in QA logbook

📋 3. Soft Skills for QA/QC Engineers

Assertive communication with contractors & client reps

Document handling and traceability
Reporting and email writing
Leadership in audits and inspections
Conflict resolution when handling NCRs

🔍 4. Key Focus Areas Before Attending Interview

TopicWhy Important
ISO 9001 clausesCore standard in QA systems
NDT methods (RT, UT, PT, MPI)Inspection skillset
Welding documentationCrucial for fabrication QA/QC
Calibration practicesUsed in all measurement tasks
Pressure testingProject critical activity
Material traceabilityClient compliance must

🧪 5. Mini Project Assignment (For Revision & Practice)

Scenario: You are a QA/QC engineer on a gas pipeline project. Prepare the following:

List of inspection checklists needed

Sample ITP for welding & NDT
A punch list format
One sample NCR & corrective action
Final QA Dossier index page

🧠 6. Bonus Tips for Freshers

Create a file of 10+ sample QA/QC forms (MIR, WIR, RFI, NCR, etc.)

Learn to read technical drawings and P&IDs
Do mock interviews with experienced QA/QC professionals
Build familiarity with ISO, ASME, and API standards

Chapter 18: MCQs – Interview & Field Challenges


Q1. What does the abbreviation NCR stand for in QA/QC?
A) National Control Requirement
B) Non-Conformance Report
C) New Contractor Request
D) Normal Calibration Record
🟩 Correct Answer: B


Q2. Which of the following is not part of a final QA/QC dossier?
A) Hydrostatic Test Report
B) Welding Procedure Specification
C) NCR Log
D) Manpower Salary Sheet
🟩 Correct Answer: D


Q3. You are at site and a weld is completed without any inspection request. What should you do first?
A) Ignore the issue
B) Issue RFI post-weld
C) Raise an NCR and investigate
D) Ask the welder to weld again
🟩 Correct Answer: C


Q4. Which test is used to verify paint thickness on coated surfaces?
A) Ultrasonic Thickness Test
B) DFT Test (Dry Film Thickness)
C) Dye Penetrant Test
D) Pressure Test
🟩 Correct Answer: B


Q5. If an equipment’s calibration certificate is expired, what should the QA/QC engineer do?
A) Use the equipment anyway
B) Manually approve readings
C) Remove from service and recalibrate
D) Ignore it for non-critical items
🟩 Correct Answer: C


Q6. What is the first action to take when a non-conformance is observed?
A) Fire the responsible person
B) Document it in an NCR
C) Inform the client only
D) Continue work
🟩 Correct Answer: B


Q7. Which of the following is a good QA/QC practice during project handover?
A) Delete old records
B) Submit final documents without index
C) Archive all QA records and provide an indexed dossier
D) Skip rejected item logs
🟩 Correct Answer: C


Q8. A client asks for ITP, but you don’t have it on site. What does this indicate?
A) Perfect documentation
B) Incomplete QA preparation
C) Well-organized QA plan
D) Updated drawings
🟩 Correct Answer: B


Q9. Who is responsible for issuing the RFI (Request for Inspection)?
A) Safety officer
B) Planning engineer
C) QA/QC engineer or inspector
D) Accountant
🟩 Correct Answer: C


Q10. What is the main purpose of a punch list during handover?
A) To evaluate salary
B) To track pending tasks and rectifications
C) To reject materials
D) To issue new tenders
🟩 Correct Answer: B




homeacademy

Home academy is JK's First e-learning platform started by Er. Afzal Malik For Competitive examination and Academics K12. We have true desire to serve to society by way of making educational content easy . We are expertise in STEM We conduct workshops in schools Deals with Science Engineering Projects . We also Write Thesis for your Research Work in Physics Chemistry Biology Mechanical engineering Robotics Nanotechnology Material Science Industrial Engineering Spectroscopy Automotive technology ,We write Content For Coaching Centers also infohomeacademy786@gmail.com