Multiple-choice questions (MCQs) on Estimation, Costing & Valuation for jkssb je civil engineer ssc je civil rrb je civil exam

50 multiple-choice questions (MCQs) on Estimation, Costing & Valuation



Methods of Estimation

  1. Which type of estimate is prepared at the initial stage of a project?
    A) Detailed estimate
    B) Preliminary estimate
    C) Revised estimate
    D) Supplementary estimate
    Ans: B

  2. Which method is most accurate for estimating building works?
    A) Plinth area method
    B) Cube rate method
    C) Detailed estimate method
    D) Approximate quantity method
    Ans: C

  3. Revised estimate is prepared when the total cost exceeds the original by more than:
    A) 2%
    B) 5%
    C) 10%
    D) 20%
    Ans: C

  4. Plinth area includes:
    A) Internal walls only
    B) External walls only
    C) Total area at floor level
    D) Carpet area
    Ans: C

  5. What does 'abstract estimate' mean?
    A) Detailed costing
    B) Summary of cost
    C) Quantity calculation
    D) Overhead analysis
    Ans: B

  6. Which of the following estimates is used to obtain administrative approval?
    A) Revised
    B) Supplementary
    C) Preliminary
    D) Detailed
    Ans: C

  7. Detailed estimate includes:
    A) Specifications only
    B) Abstract of cost
    C) Quantity and rate
    D) All of the above
    Ans: D

  8. Which estimate is prepared when the work exceeds the original scope?
    A) Preliminary
    B) Revised
    C) Supplementary
    D) Plinth area estimate
    Ans: C

  9. Which unit is used for estimation of plastering work?
    A) Cu.m
    B) Sq.m
    C) Running meter
    D) Nos.
    Ans: B

  10. Which of the following is NOT a method of approximate estimation?
    A) Plinth area method
    B) Service unit method
    C) Cube rate method
    D) Revised estimate method
    Ans: D


🔹 Rate Analysis

  1. Rate analysis is done to calculate:
    A) Quantity
    B) Cost per unit item
    C) Design load
    D) Labour wages only
    Ans: B

  2. Main components in rate analysis are:
    A) Materials only
    B) Labour only
    C) Material, labour, overheads
    D) Cost of land
    Ans: C

  3. Contractor’s profit is usually taken as:
    A) 2%
    B) 5%
    C) 10%
    D) 15%
    Ans: C

  4. Rate analysis of brickwork is done per:
    A) Sq.m
    B) Cu.m
    C) Running meter
    D) Kg
    Ans: B

  5. Lead refers to:
    A) Depth of excavation
    B) Horizontal distance of material transport
    C) Vertical height
    D) Duration of work
    Ans: B

  6. Wastage of steel in rate analysis is taken as:
    A) 1%
    B) 3%
    C) 5%
    D) 10%
    Ans: B

  7. Rate analysis helps in:
    A) Fixing tender rates
    B) Budgeting
    C) Estimating cost
    D) All of the above
    Ans: D

  8. Labour cost in rate analysis is calculated by:
    A) Per hour
    B) Per kg
    C) Per unit work
    D) Lump sum
    Ans: C

  9. In rate analysis, cost of tools and plants is usually taken as:
    A) 1%
    B) 2%
    C) 3%
    D) 5%
    Ans: C

  10. In rate analysis, curing water is included under:
    A) Labour
    B) Sundries
    C) Overheads
    D) Tools
    Ans: B


🔹 Earthwork Calculation

  1. Earthwork is calculated in:
    A) Sq.m
    B) Cu.m
    C) Kg
    D) Running meter
    Ans: B

  2. The volume of earthwork in roadwork is generally calculated using:
    A) Simpson’s Rule
    B) Mid-Sectional Area Method
    C) Average End Area Method
    D) Trapezoidal Rule
    Ans: C

  3. For uniform cross section, earthwork = area ×
    A) Width
    B) Height
    C) Length
    D) Volume
    Ans: C

  4. Lead and lift are applied in:
    A) Brickwork
    B) Painting
    C) Earthwork
    D) Flooring
    Ans: C

  5. Unit of measurement for earth filling in foundation:
    A) Cu.m
    B) Sq.m
    C) Tonnes
    D) Running meter
    Ans: A

  6. Lift refers to:
    A) Height of the building
    B) Depth of the pit
    C) Vertical distance for lifting soil
    D) Road gradient
    Ans: C

  7. Number of lifts commonly used in earthwork estimation:
    A) 1
    B) 2
    C) 3
    D) 5
    Ans: C

  8. Which method is suitable for estimating irregular earthwork?
    A) Mid-sectional area method
    B) Prismoidal formula
    C) Average end area method
    D) Centre line method
    Ans: B

  9. Bulking of sand affects:
    A) Volume estimation
    B) Steel quantity
    C) Painting area
    D) Water demand
    Ans: A

  10. Earthwork in irrigation channels is usually measured in:
    A) Sq.m
    B) Cu.m
    C) Running meter
    D) Hectares
    Ans: B


🔹 Valuation Concepts

  1. Valuation is done to find:
    A) Market value
    B) Physical condition
    C) Construction cost only
    D) Load-bearing capacity
    Ans: A

  2. The present worth of a building is called:
    A) Rate
    B) Salvage value
    C) Valuation
    D) Cost
    Ans: C

  3. The value of a building after its useful life is called:
    A) Market value
    B) Salvage value
    C) Book value
    D) Capital cost
    Ans: B

  4. The process of deduction of value due to age is called:
    A) Depreciation
    B) Salvage
    C) Obsolescence
    D) Costing
    Ans: A

  5. Book value = Original cost –
    A) Depreciation
    B) Salvage value
    C) Annual value
    D) Market rate
    Ans: A

  6. The method commonly used for valuation of land:
    A) Rental method
    B) Profit method
    C) Comparative method
    D) Annuity method
    Ans: C

  7. Sinking fund is used to compensate:
    A) Interest
    B) Depreciation
    C) Loan
    D) Capital cost
    Ans: B

  8. Scrap value is:
    A) Value at end of life
    B) Rent
    C) Book value
    D) Selling price
    Ans: A

  9. Capitalized value = Net income ×
    A) Year’s purchase
    B) Life of building
    C) Rate of return
    D) Interest rate
    Ans: A

  10. Which method is suitable for valuing cinema halls?
    A) Rental method
    B) Profit method
    C) Annuity method
    D) Cost method
    Ans: B


🔹 Mixed Questions

  1. Depreciation in valuation is generally considered as:
    A) Monthly
    B) Yearly
    C) Once in 10 years
    D) Not required
    Ans: B

  2. Estimate prepared when cost exceeds 5% of sanctioned estimate:
    A) Supplementary
    B) Revised
    C) Abstract
    D) Preliminary
    Ans: B

  3. Measurement book is used for:
    A) Drawing preparation
    B) Recording measurements
    C) Rate analysis
    D) Structural analysis
    Ans: B

  4. Purpose of plinth area estimate is to get:
    A) Floor area
    B) Carpet area
    C) Rough cost
    D) Painting cost
    Ans: C

  5. Valuation is NOT required for:
    A) Tax fixation
    B) Insurance
    C) Court settlement
    D) Load calculation
    Ans: D

  6. Annual Repair cost is generally taken as:
    A) 0.5% of cost
    B) 1% of cost
    C) 2% of cost
    D) 3% of cost
    Ans: B

  7. Typical life of an RCC structure is considered as:
    A) 15 years
    B) 50 years
    C) 75 years
    D) 100 years
    Ans: B

  8. A method of costing used in road estimation is:
    A) Service unit method
    B) Rental method
    C) Unit rate method
    D) Annuity method
    Ans: A

  9. Useful life of timber structure is generally:
    A) 10–20 years
    B) 30–40 years
    C) 70–80 years
    D) Over 100 years
    Ans: A

  10. Which one affects valuation the most?
    A) Painting cost
    B) Locality
    C) Plumbing cost
    D) Roof type
    Ans: B

homeacademy

Home academy is JK's First e-learning platform started by Er. Afzal Malik For Competitive examination and Academics K12. We have true desire to serve to society by way of making educational content easy . We are expertise in STEM We conduct workshops in schools Deals with Science Engineering Projects . We also Write Thesis for your Research Work in Physics Chemistry Biology Mechanical engineering Robotics Nanotechnology Material Science Industrial Engineering Spectroscopy Automotive technology ,We write Content For Coaching Centers also infohomeacademy786@gmail.com

إرسال تعليق (0)
أحدث أقدم