Land cannot be acquired by merely issuing notification under Section 4: Division Bench
Division Bench of the High Court ofnJammu and Kashmir and Ladakh comprising Chief Justice Pankaj Mithal and Justice Wasim Sadiq Narga has held that private land can- not be acquired by theGovernment by merely issuing notification under Section 4 of the relevant law and such pro- ceedings culminate only with the final declaration followed by an award.The Division Bench was dealing with a writ petition wherein it was submitted that the land acquisition proceedings pursuant to the notification dated December 21, 2016 have lapsed and directions should be
issued to the respondents that if they still require the land in question they may follow the procedure under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013. The petitioners submitted that their land was notified to be acquired vide notification dated December 21, 2016 issued under Section 4 of the J&K Land Acquisition Act and thereafter a meeting of District Private Negotiation Committee (DPNC) was held on July 24, 2017. The compen- sation at the rate of Rs 15.50 lakh per kanal was agreed upon but could not be final-ized as the matter was beyond the jurisdiction of the Deput Commissioner concerned. Accordingly, the matter was forwarded to the Divisional Commissioner on August 8,
2017 for his approval. The peti-
tioners alleged that without
finalizing the acquisition either
by issuing a notification under
Section 6 of the Act or the
DPNC, the respondents cannot
proceed further in the matter and
since in the meantime, the J&K
Land Acquisition Act has been
repealed, it is incumbent upon
the respondents to enter into de-
novo exercise to acquire the land
according to the provisions of
Right to Fair Compensation and
Transparency in Land
Acquisition, Rehabilitation and
Resettlement Act, 2013.
The respondents submitted
that necessary approval has been
received from the Financial
Commissioner Revenue through
Divisional Commissioner vide
letter dated June 16, 2020 for the
payment of compensation as set-
tled in DPNC.