Which of the following is not a method of
financial incentive payment?

(a) Halsey premium plan
(b) Bedaux premium plan
(c) Rowan premium plan
(d) Jhonson's premium plan

Ans : (d)
..............organisation is also called as military
organization :

(a) Functional
(b) Line
(c) Line & staff
(d) None of the above
Ans : (b)
Which is not a part of PDCA cycle (Deming
wheel)

(a) Do                     (b) Check
(c) Plan                  (d) Approve

Ans. (d)

For a repairable product, the ratio of the time
it is working satisfactorily to..............is called
availability.
(a) the total down time
(b) the test interval
(c) the total up time
(d) failure rate
Ans. (b)
In a closed loop process control system with
PID controller, ............response depends only
on the difference between set point and the
process variable
(a) proportional           (b) integral
(c) differential             (d) All of these
Ans. (d)
............is the tool for organizing the workplace
in a clean, efficient and safe manner to enhance
productivity and enable standardized working.
(a) 5S
(b) 3D
(c) 6O
(d) None of these
Ans. (a)
What is data mining used to aid in ?
(a) Operational management
(b) Analyzing past data to yield information of
value in tactical management

(c) Detecting patterns in operational data
(d) Retrieving achival data
Ans : (c)
In order that linear programming techniques
provide valid results

(a) Relations between factors must be linear
(Positive)

(b) Relations between factors must be linear
(Negative)

(c) (a) or (b)
(d) None of the above
Ans : (c)
Gantt chart provide Information about:
(a) Break even point analysis
(b) Production schedule
(c) Material handling layout
(d) Determining selling price
Ans. (b)

In manufacturing management, the term
"Dispatching" is used to describe:

(a) Dispatch of sales order
(b) Dispatch of factory mail
(c) Dispatch of finished product to the user
(d) Dispatch of work orders through shop floor

Ans : (d)
The simplex method is the basic method for
(a) Value analysis
(b) Operation research
(c) Linear programming
(d) Method anlysis
Ans : (c)
Quering theory is associated with
(a) Sales
(b) Inspection time
(c) Waiting time
(d) Production time
Ans : (c)
Which of the following production system is
characterised by the low production volume?

(a) Project Production System
(b) Job Shop Production System
(c) Batch Production System
(d) Mass Production System
Ans : (b)
Bin card is maintained by ______.
(a) costing department
(b) stores department
(c) finance department
(d) accounting department
Ans. (b)
Re-ordering level is calculated as
(a) Maximum consumption rate × Maximum re
order period

(b) Minimum consumption rate × Minimum re
order period

(c) Maximum consumption rate × Minimum re
order period

(d) Minimum consumption rate × Maximum re
order period

Ans. (a)
Which of the following is true for inventory
control?
(a) Economic order quantity has minimum total
cost per order

(b) Inventory carrying costs increases with
quantity per order

(c) Ordering cost decreases with low size
(d) All of the above
Ans. (d)
Routing is essential in the following type of
industry:

(a) Assembly industry
(b) Process industry
(c) Job order industry
(d) Mass production industry
Ans : (a)
Which one of the following is a process under
job evaluation ?

(a) Job description
(b) Job analysis
(c) Job specification
(d) All of the above
Ans : (d)
The full form of ERP is
(a) Enterprise Revenue Planning
(b) Enterprise Recovery Planning
(c) Enterprise Report Planning
(d) Enterprise Resource Planning

Ans : (d)
The following activities are to be performed
in a particular sequence for routing a
product

1. Analysis of the product and breaking it
down into components

2. Determination of the lot size
3. Determination of operations and
processing time requirement

4. Taking makes or buys decisions
The correct sequence of these activities is

(a) 1, 2, 3, 4           (b) 3, 1, 2, 4
(c) 3, 1, 4, 2            (d) 1, 4, 3, 2

Ans : (d)

Dispatching function of production planning
and control refers to:

(a) A dispatch of finished goods on order
(b) Movement of in-process material from shop
to shop

(c) Authorizing a production work order to be
launched

(d) Dispatch of bills and invoices to the
customer

Ans. (c)
In a low volume production, the dispatching
function is not concerned with issuing of
which one of the following?

(a) Work tickets
(b) Requisition of raw materials, parts and
components

(c) Route sheets to production supervisor
(d) Requisition of tools and facilities

Ans. (b)

Routing assists engineers in deciding in
advance

(a) the flow of material in the plant
(b) the methods of proper utilization of manpower
(c) the methods of proper utilization of machines
(d) the layout of factory facilities
Ans : (c)
Routing prescribes the
(a) flow of material in the plant
(b) proper utilization of man power
(c) proper utilization of machines
(d) inspection of final product
Ans : (a)
Activities involved in production, planning and
control system are listed below:

1. Planning             2. Loading
3. Scheduling        4. Despatching
5. Routing
6. Follow up
The correct sequence of these activities in
production planning and control system is:

(a) 1, 3, 5, 4, 2, 6          (b) 1, 5, 3, 4, 2, 6
(c) 1, 5, 3, 2, 4, 6          (d) 1, 3, 5, 2, 4, 6
Ans. (c)
Routing is essential in the following type of
industry

(a) assembly industry
(b) process industry
(c) job order industry
(d) mass production industry
Ans : (a)
Routing in production planning and control
refers to the

(a) Balancing of load on machines
(b) Authorization of work to be performed
(c) Progress of work performed
(d) Sequence of operations to be performed
Ans. (d)
The routing function in a production system
design is concerned with
(a) Manpower utilization
(b) Machine utilization
(c) Quality assurance of the product
(d) Optimizing material flow through the plant
Ans. (d)
Production scheduling is simpler, and high
volume of output and high labour efficiency
are achieved in the case of:

(a) Fixed position layout/
(b) Process layout
(c) Product layout
(d) A combination of line and process layout
Ans. (c)
In production, planning and control, the
document which authorizes the start of an
operation on the shop floor is the

(a) Dispatch order/
(b) Route plan
(c) Loading chart
(d) Schedule
Ans. (a)
The strategy that involves production of the
amounts demanded at any given time is :

(a) Production level strategy
(b) Chase strategy
(c) Subcontracting strategy
(d) TQM strategy
Ans : (b)
Gantt chart provides information about the :
(a) material handling
(b) proper utilisation of manpower
(c) production schedule
(d) efficient working of machine
Ans : (c)
Product layout is employed for :
(a) batch production/
(b) continuous production/melele Glheeove
(c) effective utilisation of machine
ceMeerve keâe ØeYeeJeer GheÙeesie
(d) all of the above/Ghejesòeâ meYeer
Ans : (b)



homeacademy

Home academy is JK's First e-learning platform started by Er. Afzal Malik For Competitive examination and Academics K12. We have true desire to serve to society by way of making educational content easy . We are expertise in STEM We conduct workshops in schools Deals with Science Engineering Projects . We also Write Thesis for your Research Work in Physics Chemistry Biology Mechanical engineering Robotics Nanotechnology Material Science Industrial Engineering Spectroscopy Automotive technology ,We write Content For Coaching Centers also infohomeacademy786@gmail.com

Post a Comment (0)
Previous Post Next Post