PERT CPM MCQ industrial engineering mcq
In a PERT problem, optimistic time, most likely time & pessimistic time are 1, 2 & 3 respectively, then the expected time is :
|
(a) 1 (b) 2
(c) 3 (d) 4
In PERT analysis, the time estimates of activities and probability of their occurrence follow as (a) Normal distribution curve (b) β distribution curve (c) Poisson's distribution curve (d) Binomial distribution curve Ans : (b) |
The symbol on a PERT/CPM Chart represents : (a) An ordinary event (b) A significant event representing Some mile stone (c) An event to be transferred to other network Chart (d) Dangling event |
Ans : (a)
............is a manufacturing philosophy that emphasizes careful scheduling of work, on-time delivery of zero-defect supplies and highly skilled workforce.
|
(a) PERT (b) MRP
(c) EOQ (d) JIT
PERT/CPM are (a) Analytical methods (b) Graphical method (c) Inspection techniques (d) Network techniques Ans : (d) |
In CPM network critical path denotes the: (a) path where maximum resources are used. (b) path where minimum resources are used. (c) path having zero delay (d) path that gets monitored automatically. Ans : (c) |
CPM has following time estimate :- (a) One time estimate (b) Two time estimate (c) Three time estimate (d) Four time estimate Ans : (a) |
Critical path on a PERT/CPM chart is obtained by joining the events having: |
(a) maximum slack (b) minimum slack (c) average slack (d) zero slack Ans : (d) |
Choose the statement which is correct: (a) PERT is event oriented (b) PERT is not event oriented (c) CPM is event oriented (d) CPM is not event oriented Ans : (a) |
PERT has following time estimate :- (a) One time estimate (b) Two time estimate (c) Three time estimate (d) Four time estimate Ans : (c) |
In PERT, the time estimates of activities are probabilistic and the probability of their occurrence follows : (a) binomial distribution (b) β-distribution
(c) normal distribution (d) poisson's distribution Ans : (b) |
PERT is the (a) Time oriented technique (b) Event oriented technique (c) Activity oriented technique (d) Target Oriented technique Ans : (b) |
Which one of the following is used in the value analysis of any product ?
| (a) FAST (b) CPM (c) PERT (d) MOST
Ans : (a) |
The total float on the critical path in CPM is............ (a) negative (b) positive fraction (c) positive (d) zero/ Ans. (d) |
The performance of a specific task in CPM is known as (a) Dummy (b) Event (c) Activity (d) Contract |
In CPM network cirtical path denotes the: (a) Path where maximum resources are used (b) Path where minimum resources are used (c) Path where delay of one activity prolongs the duration of completion of project (d) Path that gets monitored automatically |
In PERT, the distribution of activity times is assumed to be: (a) Normal (b) Gamma |
(c) Beta (d) Exponetial
Ans : (c) A dummy activity is used in PERT network to describe : (a) Precedence relationship (b) Necessary time delay (c) Resource restriction (d) Resource idleness |
In PERT analysis a critical activity has: (a) Maximum float (b) Zero float (c) Maximum cost (d) Minimum cost |
The expected time (te) of a PERT activity in terms of optimistic times (t0), pessimistic time (tp) and most likely time (tm) is given by:
|
Ans. (a)
The critical path of network is the path that: (a) Takes the shortest time (b) Takes the longest time (c) Has the minimum variance (d) Has the maximum variance |
Ans : (b)
In an activity has zero slack, it implies that: (a) It lives on the critical path (b) It is a dummy activity (c) The project is progessing well (d) None of the above |
Ans. (a)
The most likely time (m) is 'mode' of the: (a) Normal distribution (b) Beta distribution (c) Binomial distribution (d) None of the above |
Ans : (b)
Fulkerson's rule is connected with: (a) Numbering of event in PERT/CPM (b) The Simulatting model (c) Queuing theory (d) None of the above |
Ans. (a)
The variance of the completion time for a project is the sum of variance of: (a) All activity times/ (b) Non-critical activity times (c) Critical activity times (d) Activity times of first and last activities of the project |
Ans : (c)
CPM is the (a) Time oriented technique (b) Event oriented technique (c) Activity oriented technique (d) Target oriented technique |
Ans : (c)
KANBAN is used in: (a) Synchrounous Manufacturing |
(b) Materials Requirements Planning (c) Total Quality Management (d) Just-In-Time manufacturing |
Ans. (d)
Consider the following statements: PERT considers the following time estimates 1. Optimistic time 2. Pessimistic time 3. Most likely time (a) 1, 2 and 3 (b) 1 and 2 only (c) 3 only (d) 1 and 3 only |
Ans. (a)
Dummy activities are used in a network to: |
|
(a) Facilitate computation of slacks (b) Satisfy precedence requirements (c) Determine project completion time (d) Avoid use of resources |
A PERT activity has an optimistic time estimate of 3 days, a pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity? |
(a) 5·0 days (b) 7·5 days (c) 8·0 days (d) 8.5 days Ans. (d)
Which one of the following statements is not correct? (a) PERT is probabilistic and CPM is deterministic (b) In PERT, events are used deterministic and in CPM activities are used (c) In CPM, the probability to complete |
(d) In CPM crashing is carried the project in a given time-duration is out calculated Ans. (c) |
In CPM network critical path denotes the (a) Path where maximum resources are used (b) Path where minimum resources are used (c) Path where delay of one activity prolongs the duration of completion of project (d) Path that gets monitored automatically Ans. (c) |
PERT and CPM are : (a) techniques to determine project status (b) decision making techniques (c) charts which increase aesthetic appearance of rooms (d) aids to the decision maker
| Ans : (d) |
A big advantage of PERT over Gantt charts is that in the former case (a) activities and events are clearly shown
(b) early start and late finish of an activity are clearly marked/ (c) critical path can be easily determined (d) inter-relationship among activities is clearly shown | Ans : (d) |
CPM is the/ (a) time oriented technique (b) event oriented technique (c) activity oriented technique (d) work oriented technique | Ans : (c) |
The basic difference between PERT and CPM is that
(a) CPM deals with events and PERT with activities (b) critical path is determined in PERT only (c) costs are considered on CPM only and not in PERT (d) guessed times are used in PERT and evaluated times in CPM
| Ans : (d) |
PERT stands for (a) programme evaluation and review technique (b) project examination and review technique |
(c) project evaluation and reporting technique (d) process execution and reporting technology
| Ans : (a |
The first method invented for planning projects was (a) bar chart method (b) milestone chart (c) critical path method (CPM) (d) programme evaluation and review technique
| Ans : (a) |
The time of completing a project in network analysis is given by following time of the critical activity meeting at the final node (a) early finish (b) early start (c) late start (d) late finish |
If D is the duration, ES and EF are the earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good |
(a) EF = ES + D (b) LS = LF - D (c) LF = LS + D (d) all of the above |
The difference between the time available to do the job and the time required to do the job, is known as |
(a) event (b) float (c) duration (d) constraint
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
(a) latest start time - earliest start time (b) latest finish time - earliest finish time (EFT) (c) TL - EFT (d) all of the above |
The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as |
(a) duration (b) total float (c) free float (d) interfering float |
Pick up the correct statement about relationship between various floats |
(a) free float = total float (b) independent float = total float (c) independent float > free float (d) independent float < free float |
Ans : (d)
|
The time which results in the least possible direct cost of an activity is known as
(a) normal time (b) slow time (c) crash time (d) standard time |
PERT is (a) an analytic tool in concept (b) used for research and development projects (c) based on three time estimates for activities linking up two events (d) all of the above Ans : (d) |
Critical path on PERT/CPM chart is obtained by joining the events having
(a) maximum slack (b) minimum slack (c) average slack (d) no slack | Ans : (b) |
Activity slack or float of any event on a PERT/CPM chart is represented by |
(a) latest start time of succeeding event - earliest finish time of preceding event activity time (b) latest start time of the event - earliest start time of the event (c) latest finish time of event - earliest finish time of the event (d) anyone of the above/ | Ans : (d) |
The slack on various events at critical path will be
(a) same as at the end point (b) decreasing proportional to that at the end point (c) increasing proportional to that at the end point (d) maximum compared to other events
| Ans : (a) |
Pessimistic time is (a) the maximum time which an activity might require (b) the average time required for a job (c) the most probable time considering all conditions (d) the minimum time in which an activity can possibly be accomplished | Ans : (a) |
|
|